• Phase I:

    • December 2015 – Preliminary work began with the electrical build-out (exterior) and continued during winter break with concrete footings and columns poured in the library that will provide support for future remodeling work.
    • Spring/Summer 2016 – Exterior work will begin in April 2016. Areas to be addressed include: new safe and secure front entrance and student services area, new multi-grade STEM (Science, Technology, Engineering, and Math) Labs, remodeling of various large group instruction areas, kitchen, cafeteria, and library. Completion of these areas is scheduled to be achieved prior to the start of the 2016-17 school year, with the exception of the Student Services area and the front entrance, which is scheduled to be completed and occupied during the winter break of 2016.

     

    Phase II:

    • Summer 2017 – Updates and renovations to the facility will continue and include music, band and orchestra rooms, science classrooms, fitness and health rooms, student learning center, and stage. This phase is scheduled for completion by the start of the 2017-18 school year.

     

    Phase III:

    • Summer 2018 – This phase is scheduled to be completed by the start of the 2018-19 school year and includes gym and locker room upgrades. All remaining classrooms and hallways to receive new flooring, ceilings and locker replacement.