  • CONSTRUCTION UPDATES
    *all updates in list form below are provided by Z3 Solutions

     

    As of 08/21/18
    As of 07/24/18

    As of 06/28/18

    As of 09/19/17

    As of 08/15/17

    As of 07/19/17

    As of 01/09/17

    As of 12/01/16

    As of 08/04/16

    As of 07/15/16

    As of 06/15/16

    As of 05/27/16


    PHASE III

     

    Locker Rooms & West Gymnasium
    • Demolition of the boys and girls locker room is complete.
    • West Gym floor is protected and existing bleachers have been removed.
    • Corridor demolition surrounding the West Gym is complete.
    • Stairs at Door 1 have been removed and the entrance has been closed during construction.
    • New steel stair with concrete pan fill in complete. Railings are underway.
    • Plumbing rough in the locker rooms is complete.New masonry walls are complete. Masonry openings for new hollow metal frames are being modified and are 50% complete.
    • Demolition of the boys and girls locker rooms are complete.
    • Concrete locker bases are poured.
    • MEP ceiling rough is complete.
    • West Gym floor is protected. Existing bleachers have been removed.
    • New bleachers are installed.
    • Fire protection sprinkler lines and drops are complete.
    • Corridor demolition surrounding the West Gym is complete.
    • Floor grinding in corridors is complete.
    • Stair at Door 1 has been removed.
    • New steel stair with concrete pan fill and rails is complete.
    • Plumbing rough in the boys and girls locker rooms is complete.
    • New masonry walls are complete.
    • Ceilings are complete including electrical and HVAC trim.
    • Concrete floors and locker bases are stained.
    • Lockers are in place.
    • Final paint is underway.
    • Plumbing fixtures are set.

     

     

     

     

     

    East Gymnasium (Auditorium)

    • Demolition is in progress.
    • Gas and electrical roof piping has been removed, to be reinstalled upon new roof completion.
    • Existing roof membrane has been removed. New roof installation is complete, less stoning and perimeter metal coping.
    • Roof top unit curb is set and flashed by the roofer
    • Masonry wall restoration is underway and new wall construction has begun.
    • Demolition is complete.
    • Gas and electrical roof piping has been removed and to be reinstalled upon new roof completion.
    • Existing roof membrance has been removed. New roof installation is complete, lesson stoning and perimeter metal coping/flashing.
    • Roof top unit curb is set and flashed by the roofer.
    • Masonry wall restoration and new wall construction is complete.
    • New limestone infill of existing blocked up window openings is complete.
    • New stage ramp has been poured.
    • HVAC ceiling ductwork has been delivered and install has begun.

      

    1st Floor Classrooms and Corridors

    • Demolition work is complete.
    • Masonry work is complete in the orchestra room and 90% complete in the bathrooms.
    • Ceiling MEP rough-in work is underway and is 90% complete.
    • Underground plumbing is complete and inspected including concrete infill.
    • Air handler unit 1 has been delivered.
    • Cabinet unit heaters are set.
    • Plastic patch of corridor walls are 50% complete.
    • Underground plumbing complete and inspected including concrete infill.
    • Drywall partitions and soffits are 95% complete.
    • Prepping of glazed block walls for painting is in progress.
    • Convector cover installation has begun.
    • Demolition work is complete.
    • Corridor floor grinding is complete.
    • Concrete bases for lockers are complete.
    • Ceiling MEP rough-in work is complete.
    • Underground plumbing complete and inspected including concrete infill.
    • Cabinet unit heaters are set.
    • Drywall partitions and soffits are complete.
    • Glazed block walls for painting is complete.
    • Acoustical ceilings and MEP trim is complete.
    • Classroom carpet is complete.
    • Millwork installation is complete.
    • Market board installation is complete.
    • Corridor flooring is complete.

     

    2nd Floor Classrooms and Corridors

    • Demolition work is complete.
    • Masonry wall work is underway and is 85% complete.
    • Electrical rough-in work is complete
    • Air handler unit 2 has been delivered and associated duct work is on site.
    • Masonry wall work is complete.
    • Toilet room plumbing rough is complete and inspected.
    • MEP ceiling and wall rough is complete.
    • Drywall soffits and partitions are 95% complete.
    • New window installation is 85% complete.
    • Cabinet unit heaters are set.
    • Concrete locker bases are poured.
    • Corridor floor prep is complete.
    • Toilet room ceramic tile work has commenced.
    • Ceiling grid work is underway.
    • Demolition work is complete.
    • Masonry wall work is complete.
    • Toilet room plumbing rough is complete and inspected.
    • MEP ceiling and wall rough is complete.
    • Drywall soffits and partitions are complete.
    • New window installation is complete.
    • Cabinet unit heaters are set.
    • Concrete locker bases are poured.
    • Corridor flooring is complete.
    • Toilet room ceramic tile is complete.
    • Plumbing fixtures are set.
    • Classroom construction is complete including flooring, ceilings, millwork, marketboard and painting.

     

    3rd Floor Classrooms and Corridors

    • Demolition work is complete.
    • Unanticipated abatement work is complete.
    • Unanticipated concrete repair work is complete.
    • Underground plumbing work is complete and plumbing inspection is pending. Plumbing wall rough is 50% complete.
    • Ductwork is on site and 70% complete.
    • Electrical ceiling rough-in work is complete.
    • Stud framing work has begun and is 20% dcomplete
    • Mechanical piping is complete.
    • Masonry work has begun and is 20% complete. 
    • Masonry wall work is complete.
    • Toilet room plumbing rough is complete and inspected.
    • MEP ceiling and wall rough is complete.
    • Drywall soffits and partitions are 95% complete.
    • New window installation is 85% complete.
    • Cabinet unit heaters are set.
    • Concrete locker bases are poured.
    • Corridor floor prep is complete.
    • Toilet room ceramic tile work has commenced.
    • Ceiling grid work is underway.
    • Demolition work is complete.
    • Masonry wall work is complete.
    • Toilet room plumbing rough is complete and inspected.
    • MEP ceiling and wall rough is complete.
    • Drywall soffits are partitions are complete.
    • New window installation is complete.
    • Cabinet unit heaters are set.
    • Concrete locker bases are poured.
    • Corridor flooring is complete.
    • Toilet room ceramic tile is complete.
    • Plumbing fixtures are set.
    • Classroom construction is complete including flooring, ceilings, millwork, marketboard and painting.

      

     

    PHASE II

    Gymnasium

    • Drinking fountain modifications are planned for Phase III.
    • Gym floor system is complete.
    • Gym floor sleeve installation is pending design.
    • Final clean complete.
    • Roofing work is complete, manufacturer’s review and acceptance is complete.
    • Ceiling Acoustical Panel work is 100% complete this is inclusive of the break metal enclosure at the ridge.
    • Painting work is complete. Overspray clean-up is pending.
    • Abatement work is complete.
    • Gym Floor sleeper and underlayment system is 35% complete.
    • Roofing work is complete
    • Ceiling Acoustical Panel and Painting work is 95% complete
    • Abatement work complete

     

    Health & Fitness

    • Corridor, health, and storage room floors are complete.
    • Health, fitness, and corridor walls are painted.
    • Masonry Walls Complete. Misc. soaps pending.
    • Perimeter knee walls are framed with drywall installed and electrical rough-in complete.
    • MEP rough-in work is 90% complete.
    • Underside of roof deck is painted white.
    • Concrete locker bases are complete.
    • 2nd floor access platform has been removed and the window is being reinstalled.
    • Demolition work is complete
    • Abatement work is complete
    • MEP rough-in work has begun
    • RTU-15 curb and unit have been set with related roof patch complete
    • Concrete floor patch and floor penetration infill work is complete
    • 2nd floor access platform is in place

     

    Orchestra Room & 1st Floor Bathrooms

    • Bathrooms are 100% complete and in use for the school year.
    • Ceiling grid and tile work is 100% complete.
    • Air Handler Unit #1 has been set and functional.
    • Lockers are installed and in use for the 2017-18 school year.
    • Millwork, marker boards, and doors are 100% complete.
    • School supplied furniture installation is underway.
    • Final clean is complete.
    • Ceramic floor and wall tile is complete. Awaiting grout.
    • Masonry work is 100% complete.
    • Ceiling MEP rough-in work is 100% complete.
    • Ceiling grid is underway.
    • Air Handler Unit #1 has been set and final connections underway.
    • Locker bases have been poured
    • Painting is underway.
    • Corridor lights are 80% complete.
    • Demolition work is complete
    • Masonry work is complete in the Orchestra room and 90% complete in the bathrooms.
    • Ceiling MEP rough-in work is underway and is 90% complete.
    • Underground plumbing complete and insepcted including concrete infill.
    • Air Handler Unit #1 has been delivered.

     

    Band & Music Rooms

    • Air Handler Unit #2 is installed and operational.
    • Painting work is 100% complete.
    • Room and corridor floor work is 100% complete including repair of access hatch.
    • Final clean is complete.
    • Ceiling Grid work is complete.
    • Masonry wall work is underway and is 100% complete.
    • Light fixture installation is 100% complete.
    • Air Handler Unit #2 is installed and final connections are underway.
    • Concrete ramps are 100% complete.
    • Painting is 80% complete. Awaiting final coat.
    • Corridor floor prep work is underway.
    • Corridor soffit work is 100% complete.
    • Demolition work is complete
    • Masonry wall work is underway and 85% complete
    • Electrical rough-in work is complete
    • Air Handler Unit #2 is delivered and associated duct work is on site

     

    Math & Science Rooms

    • Rooms were turned over for use at the start of the 2017-18 school year.
    • Concrete curbs and slab on grade modifications complete.
    • Plumbing underground and in wall rough-in complete.
    • Unanticipated wall patch in 2nd and 3rd floor science prep rooms is complete.
    • Ceiling grid is 100% complete.
    • Light fixtures are 100% complete.
    • Drywall walls and soffits are 100% complete.
    • Painting is 80% complete.
    • Epoxy floors are complete and protected.
    • Millwork installation is underway.
    • Demolition work is complete
    • Unanticipated abatement work is complete
    • Underground plubming work is complete and plumbing inspection pending
    • Ductwork on site, work is 70% complete
    • Electrical ceiling rough-in work is complete
    • Stud framing work has begun and is 20% complete
    • Mechanical piping is complete
    • Masonry work has begun and is 20% complete

     

    Exterior Courtyard

    • ComEd switch over to be performed over Thanksgiving Break.
    • Demolition of the courtyard is underway and graded. Only area to be removed is the sidewalk at Rutledge Hall.
    • Concrete curbs and slab on grade are 100% complete.
    • ComEd switch over to be performed over Thanksgiving Break.
    • Landscaping is 100% complete.
    • All exterior glazing is 100% complete. Caulking is underway.
    • Demolition of the courtyard is underway and graded
    • Planter curbs are poured
    • Conduit runs for August 14th, ComEd work is complete
    • Planter soil will be placed prior to flatwork

     

     

    PHASE I

    General:

    • Installation of construction fence around the school for safety
    • Installation of Jersey barriers

    “New” cafeteria area:

    • All MEP rough install is complete in cafeteria and kitchen
    • New cafeteria kitchen epoxy flooring in the process of being installed
    • Kitchen walk in freezer and cooler are set in place
    • Cafeteria drywall framing and ceiling grid is underway
    • Install kitchen hood
    • Sprinkler system rough in
    • Cafeteria build - masonry walls
    • Electrical rough in kitchen
    • HVAC - kitchen and ceiling rough in
    • Start MEP rough in dining area
    • Plumbing rough in
    • Completed demolition
    • Grade/pour cafeteria slab on grade
    • Cut off/disconnection of mechanical, electrical, and plumbing in this area
    • Demolition of walls and removal of floors
    • Plumbing “roughed in”
    • Pour slab on grade
    • Masonry walls built

     

    “New” student services area:

    • Administration offices are complete and occupied over Winter Break
    • The main entrance is complete with the exception of the West Wall security glass
    • The 1st floor Octagon space is complete including the installation of the jaguar logo
    • Water infiltration originating from the Octagon tower has been rectified
    • Plaster systems on the exterior canopy roof is complete
    • Punch list work is nearing completion
    • All steel work is complete with exception of in progress steel canopy framing
    • Exterior masonry wall construction is copmlete. Brick cleaning and joint caulking is underway
    • Permanent roof work is in progress sequenced with 3rd floor roof, followed by 1st floor roof work and ending with the 2nd floor roof and canopy
    • The center stair is complete and available for emergency exiting duty
    • Skylight install at roof of the center stair commenced on 11/10/16
    • Mechanical, plumbing, and electrical is 75% complete
    • All foundation walls are complete
    • Structural steel is 75% complete
    • Masonry walls on west side are in progress
    • Backfill west foundation walls
    • Complete concrete footings
    • Set roof steel
    • Second floor masonry
    • Start structural steel erection
    • Complete west footings foundations
    • Demolition of area (75% completed)
    • Start elevation of elevator pit
    • Removal of playground equipment
    • Layout for foundation
    • Cut area to sub grade
    • Dig for footings
    • Pour footings
    • Pour foundation walls
    • Backfill Foundation walls
    • Start masonry walls

     

    STEM Courtyard

    • Library millwork Room E340 has been reconfigured and is complete
    • Punchlist work is 100% complete
    • Drinking fountain revisions have been completed utilizing bottle filler
    • All concrete floors and toppings are complete except for maintenance and prep storage
    • Roofing over the 3-story addition is complete
    • Window installation is underway
    • Relocation of the courtyard HW piping is 100% complete
    • Framing of drywall partitions is 75% complete
    • HVAC and electrical rough is being completed
    • Roof steel and deck
    • Pour 2nd/3rd floor toppings
    • Set roof steel and deck
    • Exterior masonry on curved wall
    • Set second floor precast
    • Set second floor steel
    • Protect new concrete for demo
    • Library interior demo completed
    • Shoring and temp walls
    • Steel erect columns and first floor beams
    • Set first floor precast
    • Set second floor precast
    • Complete library demolition
    • Backfill HW piping
    • Saw cut, excavation, and weld/install HW piping
    • Drain system and connect
    • Removal of site concrete
    • Excavation for footings
    • Pour footings
    • Pour foundation walls
    • Protect new concrete for demo
    • Start demo

     

    “New” Fine Arts area

    • The Map of the World is underway
    • All walls are complete
    • All MEP rough is complete
    • Ceiling grid work has started
    • Drywall taping and prime coat has started
    • Begin interior walls
    • Set HM frames
    • Patch concrete north rooms
    • Complete underground plumbing
    • MEP ceiling rough in
    • Demo north side of room 136
    • Demo south side of room 130
    • Abatement in kitchen area
    • Underground plumbing
    • Patch concrete south rooms


    Site Development

    • Asphalt pavement binder course has been installed. Surface coat will be applied in the spring.
    • New bollards are on site
    • Asphalt pavement performed during week of 11/22/16
    • All underground water retention piping is installed and complete
    • Lawn irrigation piping is installed
    • Installation of sod is underway
    • Installation of the new sanitary sewer piping in the courtyard is underway
    • Istallation of the new storm sewer piping in the courtyard is also underway

     

    In conjunction with the Lincoln Hall Construction Project, the kitchens at both Rutledge Hall and Todd Hall will be remodeled. On May 25th, demolition began in both kitchens to start these remodeling projects.

     

    TODD HALL KITCHEN

    • Punchlist is complete
    • Requested adjustments are 99% complete
    • Epoxy flooring is complete
    • Kitchen equipment being delivered
    • Finish out of the ceiling system, acoustical tiles and lighting is underway
    • Paint walls
    • Set roof handrails
    • Gypsum board ceiling framing
    • MEP ceiling and wall rough
    • Demolition
    • Underground plumbing
    • Set make up air unit
    • Set steel for exhaust fans
    • Install exhaust fans
    • Concrete slab on grade

     

    RUTLEDGE HALL KITCHEN

    • Punchlist is complete
    • Requested adjustments are 99% complete
    • Epoxy flooring is complete
    • Kitchen equipment being delivered
    • Finish out of the ceiling system, acoustical tiles and lighting is underway
    • Paint walls
    • Acoustical grid framing
    • Set roof handrails
    • MEP ceiling and wall rough
    • Install music storage roof and gutter
    • Demolition
    • Music storage foundations
    • Trash enclosure concrete
    • Exterior masonry
    • Underground plumbing
    • Concrete slab-on-grade
    • Set steel for exhaust fans